In 2005, OMOX Development Company focused its efforts on ensuring the implementation of development projects in the southwest of Kyiv.

These are the areas of Sviatopetrivske and Petropavlivska Borshchahivka, Chaiky, Bilohorodka and Stoianka Villages.

The company designed and started construction, followed by commissioning, of water supply and sanitation systems, electricity, gas, and heat supply in these settlements.

The project started with a large-scale laying of utilities, namely the construction of a water pipeline and a water treatment plant with a consumption capacity of 36,000 m3 per day, a 1,200 mm gravity-fed sanitary sewer, a 110-kilowatt cable line, a distribution substation and 12 transformer substations.

A total of 70 kilometres of utility networks have been laid, worth UAH 250 million. This engineering infrastructure is capable of providing life to a city with a population of 300,000.